Habbep Dam Removal
|
Request Date: 5/14/2026 10:17:36 PM
Open Date:
Closing Date: 6/10/2026 10:00 AM
Intent To Bid Deadline:
Est. Dollar Value: $0.00
RFQ Number:
|
 |
FRIENDS OF THE WINOOSKI RIVER
Po Box 777
Montpelier,
VT
05602
|
Locations:
Washington
Keywords: Construction (Non Building), Landscaping, General Contractor, Stream Restoration
Bid Description:
The Habbep Dam on the Stevens Branch will be removed along with accumulated sediment. Work tasks will generally involve removal of the concrete dam (~320 CY) and associated remains; removal of trees; sediment removal and haul from river (~15,300 CY) and floodplain (~1,600 CY); invasive species handling; stream channel restoration using onsite bed materials; floodplain and stream restoration with wood; armoring; and site restoration.
Special Instructions: Plans are too large to attach. Please email Jessica Louisos for the plans.
|
| Site Visit: |
Date: 5/22/2026 11:00:00 AM |
Mandatory Site Visit |
Meet at the project site. Parking is available at 54 Mill Street, Barre. A second stop will be made at Parkside Terrace to view the upper portion of the project. |
 |
 |
 |
|