Bid Description:
Project Scope:
The contractor will be responsible for eight sites which includes the removal and diposal of
debris, and the purchasing and hauling of materials unless other wise indicated.
Brook Road
Site 1 - 43-58-32 lat 72-28-49 long – West Side of Road North of Allen Farm. Repair
slope/replace culvert 75 ft x 20 ft. Excavate 222 Cy yards and replace with similar amount of
Stone Fill Type IV. Culvert provided by Town.
Site 2 - 43-58-45 lat 72-28-53 long – Near Joe Compos. Replace culvert, fix outlet.25ft x 10ft.
Excavate 37 CY and replace with similar amount of Stone Fill Type IV. Culvert provided by
Town.
Site 3 - 43-59-44 lat 72-29-20 long – Near Button Farm. Repair/Reestablish ditch 150 ft x 6 ft
Excavate 33 CY replace with similar amount of Stone fill IV and 1 -1/2” crushed stone. Material
provided and hauled by town.
Site 4 – 43-59-52 lat 72-29-20 – East side of Road, south of Pent Road – Repair uphill slide area
and reestablish ditch 75ft x 20 feet excavate 17 CY and replace with similar amount of Stone Fill
Type I and 8 CY 1 – 1/2 “ crushed Stone
Site 5 – North of Pent Road. Repair/reestablish ditch. 300ft x 6ft. Excavate 66 CY material,
replace with similar amount of Stone Fill Type 1and 33 CY 1 -1/2” Crushed Stone. Material
provided and hauled by town.
Hook Road
Site 1 - 43-58-51 lat 72-30-10 long by Rick Allen’s. Fix shoulder of road and ditch. 200ft x 8ft
Excavate 59 CY of material, replace with similar amount of Stone Fill Type I and 29 CY 1 – ½”
crushed stone. Material provided and hauled by town.
Site 2 - 43-58-51 lat 72-30-10 long – By cemetery. Fix shoulder of road and ditch. Replace
Culvert. 1320 Ft x 8. Excavate 391 CY material, replace with similar amount of Stone Fill Type
1 and 195 CY 1 -1/2” Crushed Stone. Materials and culvert provided and hauled by Town.
Pent Road - 44-00-32 lat 72-29-24 long – by Coburn’s Replace undersized culvert and stone line
ditch. 550 ft x 8ft Excavate 163 CY material, replace with similar amount of Stone Fill Type 1
and 81 CY 1 -1/2” Crushed Stone. Materials and culvert provided and hauled by Town. Town will resurface road.
Special Instructions: Bidders should note that a preconstruction meeting with the Stream Alterations Engineer may be
required prior to the start of work. The Stream Alterations Engineer for this project is Jaron